PROPOSED stable/juno releases
Constraints:
- Juno release Oct 16
- Kilo Design Summit Nov 4-7
- Kilo milestones
- Kilo-1 milestone: Dec 18
- Kilo-2 milestone: Feb 5
- Kilo-3 milestone, feature freeze: Mar 19
- 2015.1 ("Kilo") release: Apr 30
- L Design Summit: May 18-22
DRAFT
2014.2.1 Nov 27 2014 (3 weeks before k1) apevec 2014.2.2 Jan 29 2015 (1 week before k2) Chuck 2014.1.4 Feb 19 2015 (2 weeks after k2) apevec 2014.2.3 Apr 9 2015 (3 weeks before final Kilo) Adam 2015.1.1 end Jun 2015 2014.1.5 - last planned, date TBD July 2015 2015.1.2 Aug 2015 2014.2.4 date TBD, after L-3 release Sep 2015 2015.1.3 Oct 2015 2015.2.1 end Nov 2015 2014.2.5 - last planned, Jan 2016 if we stick to 15 months support