Difference between revisions of "Talk:StableBranchRelease"
(→PROPOSED stable/juno releases) |
|||
(4 intermediate revisions by 2 users not shown) | |||
Line 1: | Line 1: | ||
− | ==== '''PROPOSED''' stable/ | + | ==== '''PROPOSED''' stable/* point releases ==== |
Constraints: | Constraints: | ||
* Juno release Oct 16 | * Juno release Oct 16 | ||
* Kilo Design Summit Nov 4-7 | * Kilo Design Summit Nov 4-7 | ||
− | |||
** Kilo-1 milestone: Dec 18 | ** Kilo-1 milestone: Dec 18 | ||
** Kilo-2 milestone: Feb 5 | ** Kilo-2 milestone: Feb 5 | ||
** Kilo-3 milestone, feature freeze: Mar 19 | ** Kilo-3 milestone, feature freeze: Mar 19 | ||
− | ** 2015.1 | + | ** Kilo Release (2015.1.0) Apr 30 |
− | + | * L Design Summit May 18-22 | |
+ | ** liberty-1 Jun 25 | ||
+ | ** liberty-2 Jul 30 | ||
+ | ** liberty-3 Sep 3 | ||
+ | ** Liberty Release (2015.2.0) Oct 15 | ||
+ | * M Design Summit (Tokyo) Oct 26-30 | ||
'''DRAFT''' | '''DRAFT''' | ||
− | 2014.2.1 Nov 27 2014 (3 weeks before k1) | + | 2014.2.1 Nov 27 2014 (3 weeks before k1) apevec |
− | 2014.2.2 Jan 29 | + | 2014.2.2 Jan 29 2015 (1 week before k2) Chuck |
− | 2014.2.3 Apr 9 2015 (3 weeks before final Kilo) | + | 2014.1.4 Feb 19 2015 (2 weeks after k2) apevec |
− | 2014.1. | + | 2014.2.3 Apr 9 2015 (3 weeks before final Kilo) Adam |
− | 2015.1.1 | + | 2014.1.5 - last planned, June 2015 apevec |
− | + | 2015.1.1 early July 2015 apevec | |
− | 2015.1.2 | + | 2015.1.2 late Sep 2015 Chuck |
− | 2014.2.4 | + | 2014.2.4 - last planned, Nov 2015 apevec |
− | 2015.1.3 | + | 2015.1.3- last planned, Jan 2016 TBD relmgr |
− | |||
− | |||
'''DRAFT''' | '''DRAFT''' |
Latest revision as of 13:20, 30 June 2015
PROPOSED stable/* point releases
Constraints:
- Juno release Oct 16
- Kilo Design Summit Nov 4-7
- Kilo-1 milestone: Dec 18
- Kilo-2 milestone: Feb 5
- Kilo-3 milestone, feature freeze: Mar 19
- Kilo Release (2015.1.0) Apr 30
- L Design Summit May 18-22
- liberty-1 Jun 25
- liberty-2 Jul 30
- liberty-3 Sep 3
- Liberty Release (2015.2.0) Oct 15
- M Design Summit (Tokyo) Oct 26-30
DRAFT
2014.2.1 Nov 27 2014 (3 weeks before k1) apevec 2014.2.2 Jan 29 2015 (1 week before k2) Chuck 2014.1.4 Feb 19 2015 (2 weeks after k2) apevec 2014.2.3 Apr 9 2015 (3 weeks before final Kilo) Adam 2014.1.5 - last planned, June 2015 apevec 2015.1.1 early July 2015 apevec 2015.1.2 late Sep 2015 Chuck 2014.2.4 - last planned, Nov 2015 apevec 2015.1.3- last planned, Jan 2016 TBD relmgr
DRAFT