Dates Overview

Nova roughly follows the general release schedule.

  • Feb 26-Mar 2: Project Team Gathering
  • Apr 19: r-1 milestone, nova spec freeze
  • May 21-24: Summit
  • Jun 7: r-2 milestone
  • Jul 19: non-client library (oslo, os-vif, os-brick, os-win, os-traits, etc) release freeze
  • Jul 26: r-3 milestone, Feature Freeze, final python-novaclient release, requirements freeze, Soft String Freeze
  • Aug 9: RC1 and Hard StringFreeze
  • Aug 23: Last day for release candidates
  • TBD: S PTG in TBD
  • Aug 30: Rocky release

Special review days

  • Mar 27: Rocky spec review day

Virtual Sprint

  • None scheduled

FAQs