Difference between revisions of "Nova/Queens Release Schedule"
< Nova
(Created page with "= Dates Overview = Nova roughly follows the [http://releases.openstack.org/queens/schedule.html general release schedule]. * TODO(mriedem): important dates = Special review...") |
(→Dates Overview) |
||
Line 3: | Line 3: | ||
Nova roughly follows the [http://releases.openstack.org/queens/schedule.html general release schedule]. | Nova roughly follows the [http://releases.openstack.org/queens/schedule.html general release schedule]. | ||
− | * | + | * Sept 11-15: Project Team Gathering |
+ | * Oct 19: q-1 milestone | ||
+ | * Nov 6-8: Summit | ||
+ | * Dec 7: q-2 milestone | ||
+ | * Jan 18: non-client library (oslo, os-vif, os-brick, os-win, os-traits, etc) release freeze | ||
+ | * Jan 25: q-3 milestone, Feature Freeze, final python-novaclient release, requirements freeze, Soft String Freeze | ||
+ | * Feb 8: RC1 and Hard StringFreeze | ||
+ | * Feb 22: Last day for release candidates | ||
+ | * Feb 28: Queens release | ||
= Special review days = | = Special review days = |
Revision as of 02:42, 7 September 2017
Dates Overview
Nova roughly follows the general release schedule.
- Sept 11-15: Project Team Gathering
- Oct 19: q-1 milestone
- Nov 6-8: Summit
- Dec 7: q-2 milestone
- Jan 18: non-client library (oslo, os-vif, os-brick, os-win, os-traits, etc) release freeze
- Jan 25: q-3 milestone, Feature Freeze, final python-novaclient release, requirements freeze, Soft String Freeze
- Feb 8: RC1 and Hard StringFreeze
- Feb 22: Last day for release candidates
- Feb 28: Queens release
Special review days
- ?
Virtual Sprint
- None scheduled
FAQs
Please see: Nova/Process and Nova/Mentoring