Jump to: navigation, search

Difference between revisions of "Nova/Queens Release Schedule"

(Created page with "= Dates Overview = Nova roughly follows the [http://releases.openstack.org/queens/schedule.html general release schedule]. * TODO(mriedem): important dates = Special review...")
 
(Dates Overview)
 
(3 intermediate revisions by the same user not shown)
Line 3: Line 3:
 
Nova roughly follows the [http://releases.openstack.org/queens/schedule.html general release schedule].
 
Nova roughly follows the [http://releases.openstack.org/queens/schedule.html general release schedule].
  
* TODO(mriedem): important dates
+
* Sept 11-15: Project Team Gathering
 +
* Oct 19: q-1 milestone, nova spec freeze
 +
* Nov 6-8: Summit
 +
* Dec 7: q-2 milestone
 +
* Jan 18: non-client library (oslo, os-vif, os-brick, os-win, os-traits, etc) release freeze
 +
* Jan 25: q-3 milestone, Feature Freeze, final python-novaclient release, requirements freeze, Soft String Freeze
 +
* Feb 8: RC1 and Hard StringFreeze
 +
* Feb 22: Last day for release candidates
 +
* Feb 26: Rocky PTG in Dublin
 +
* Feb 28: Queens release
  
 
= Special review days =
 
= Special review days =
  
* ?
+
* October 3rd: Queens spec review day
  
 
= Virtual Sprint =
 
= Virtual Sprint =

Latest revision as of 21:17, 21 December 2017

Dates Overview

Nova roughly follows the general release schedule.

  • Sept 11-15: Project Team Gathering
  • Oct 19: q-1 milestone, nova spec freeze
  • Nov 6-8: Summit
  • Dec 7: q-2 milestone
  • Jan 18: non-client library (oslo, os-vif, os-brick, os-win, os-traits, etc) release freeze
  • Jan 25: q-3 milestone, Feature Freeze, final python-novaclient release, requirements freeze, Soft String Freeze
  • Feb 8: RC1 and Hard StringFreeze
  • Feb 22: Last day for release candidates
  • Feb 26: Rocky PTG in Dublin
  • Feb 28: Queens release

Special review days

  • October 3rd: Queens spec review day

Virtual Sprint

  • None scheduled

FAQs

Please see: Nova/Process and Nova/Mentoring