Revision as of 15:52, 23 March 2017
Dates Overview
Nova roughly follows the general release schedule.
- Feb 20-24: Project Team Gathering
- Apr 4: spec review sprint
- Apr 13: p-1 milestone, Nova Spec Freeze
- May 8-12: Summit
- Jun 8: p-2 milestone
- Jul 20: non-client library (oslo, os-vif, os-brick, os-win, os-traits, etc) release freeze
- Jul 27: p-3 milestone, Feature Freeze, final python-novaclient release, requirements freeze, Soft String Freeze
- Aug 10: RC1 and Hard StringFreeze
- Aug 31: Pike release
Special review days
- Tuesday April 4th, spec review day.
Virtual Sprint
- None scheduled
FAQs
Please see: Nova/Process and Nova/Mentoring