* Feb 20-24: Project Team Gathering
 
* Feb 20-24: Project Team Gathering
* Apr 4: spec review sprint
+
* April 4: spec review sprint
* Apr 13: p-1 milestone, Nova Spec Freeze
+
* April 13: p-1 milestone, Nova Spec Freeze
 +
* April 25: [http://lists.openstack.org/pipermail/openstack-dev/2017-April/115704.html bug spring cleaning day]
 
* May 8-12: Summit
 
* May 8-12: Summit
 
* Jun 8: p-2 milestone
 
* Jun 8: p-2 milestone

Revision as of 15:26, 20 April 2017

Dates Overview

Nova roughly follows the general release schedule.

  • Feb 20-24: Project Team Gathering
  • April 4: spec review sprint
  • April 13: p-1 milestone, Nova Spec Freeze
  • April 25: bug spring cleaning day
  • May 8-12: Summit
  • Jun 8: p-2 milestone
  • Jul 20: non-client library (oslo, os-vif, os-brick, os-win, os-traits, etc) release freeze
  • Jul 27: p-3 milestone, Feature Freeze, final python-novaclient release, requirements freeze, Soft String Freeze
  • Aug 10: RC1 and Hard StringFreeze
  • Aug 31: Pike release

Special review days

  • Tuesday April 4th, spec review day.

Virtual Sprint

  • None scheduled

FAQs

Please see: Nova/Process and Nova/Mentoring