Dates Overview

Nova roughly follows the general release schedule.

  • Oct 25-28: Design summit in Barcelona
  • Nov 17: o-1 milestone, spec approval freeze
  • Dec 15: o-2 milestone
  • Jan 19: final non-client library release (oslo)
  • Jan 26: o-3 milestone, final python-novaclient release, FeatureFreeze, Soft StringFreeze
  • Feb 2: RC1 and Hard StringFreeze
  • Feb 23: Ocata release

Special review days

Virtual Sprint

  • TBD