Difference between revisions of "Nova/Mitaka Release Schedule"
< Nova
John Garbutt (talk | contribs) m |
|||
(4 intermediate revisions by 2 users not shown) | |||
Line 2: | Line 2: | ||
Nova roughly follows the general scheduler: [[Mitaka_Release_Schedule]] | Nova roughly follows the general scheduler: [[Mitaka_Release_Schedule]] | ||
+ | |||
+ | PLEASE NOTE, THESE DATES BELOW HAVE NOT YET BEEN CONFIRMED, ITS JUST A PROPOSAL. | ||
* Dec 1-3: mitaka-1 | * Dec 1-3: mitaka-1 | ||
− | * Dec 3: spec freeze | + | * Dec 3: Nova spec freeze |
* Jan 19-21: mitaka-2 | * Jan 19-21: mitaka-2 | ||
− | * Jan 21: non-priority feature freeze | + | * Jan 21: Nova non-priority feature freeze |
* Jan 26-28: Nova Midcycle (TBC) | * Jan 26-28: Nova Midcycle (TBC) | ||
* Feb 25: FinalLibraryRelease, and feature proposal freeze | * Feb 25: FinalLibraryRelease, and feature proposal freeze | ||
Line 15: | Line 17: | ||
OpenStack wide tracking of current progress: http://status.openstack.org/release/ | OpenStack wide tracking of current progress: http://status.openstack.org/release/ | ||
− | |||
= Special review days = | = Special review days = | ||
Line 28: | Line 29: | ||
** Follow this process: https://wiki.openstack.org/wiki/BugTriage and https://wiki.openstack.org/wiki/Nova/BugTriage | ** Follow this process: https://wiki.openstack.org/wiki/BugTriage and https://wiki.openstack.org/wiki/Nova/BugTriage | ||
** TODO - a bug fix day? | ** TODO - a bug fix day? | ||
+ | |||
+ | = Virtual Sprint = | ||
+ | |||
+ | * December 8th and 9th: Virtual API document sprint | ||
+ | ** Focus on improve nova api document http://lists.openstack.org/pipermail/openstack-dev/2015-November/079220.html | ||
Latest revision as of 13:38, 12 November 2015
Dates Overview
Nova roughly follows the general scheduler: Mitaka_Release_Schedule
PLEASE NOTE, THESE DATES BELOW HAVE NOT YET BEEN CONFIRMED, ITS JUST A PROPOSAL.
- Dec 1-3: mitaka-1
- Dec 3: Nova spec freeze
- Jan 19-21: mitaka-2
- Jan 21: Nova non-priority feature freeze
- Jan 26-28: Nova Midcycle (TBC)
- Feb 25: FinalLibraryRelease, and feature proposal freeze
- Mar 1-3: mitaka-3, and FeatureFreeze, SoftStringFreeze, RequirementsFreeze, FinalClientLibraryRelease
- Mar 15-17: RC1 and HardStringFreeze
- April 7, 2016: Mitaka Release
OpenStack wide tracking of current progress: http://status.openstack.org/release/
Special review days
Generally on a Thursday, set aside a day for reviews as a community:
- November 19: Spec Review Day
- December 17th: non-priority feature review bash day
- Focus on low priority NeedCodeReview blueprints: https://blueprints.launchpad.net/nova/mitaka
- February 4th: bug triage day
- Follow this process: https://wiki.openstack.org/wiki/BugTriage and https://wiki.openstack.org/wiki/Nova/BugTriage
- TODO - a bug fix day?
Virtual Sprint
- December 8th and 9th: Virtual API document sprint
- Focus on improve nova api document http://lists.openstack.org/pipermail/openstack-dev/2015-November/079220.html
All of these involve hanging out in #openstack-nova and working together to try and improve the statistics mentioned above.
FAQs
Please see: Nova/Process and Nova/Mentoring