We are aligning with: [[Liberty_Release_Schedule]]
 
We are aligning with: [[Liberty_Release_Schedule]]
 +
But there are some extra deadlines around Priority features.
 +
 +
If you are new to Nova, please read this first: https://wiki.openstack.org/wiki/Nova/Mentoring
  
But there are some extra deadlines to around Priority features.
 
  
 
== Dates overview ==
 
== Dates overview ==
  
 
* June 23-25: liberty-1 -- spec freeze for L, backlog stays open
 
* June 23-25: liberty-1 -- spec freeze for L, backlog stays open
 +
 +
* July 16: non-priority feature proposal freeze
 
* July 21-23: mid-cycle meetup
 
* July 21-23: mid-cycle meetup
* July 28-30: liberty-2 -- non-priority feature freeze
+
* July 30: liberty-2 -- non-priority feature freeze
* September 1-3: liberty-3 -- align with string freeze, etc, open specs for M
 
  
 +
* August 18: Feature Proposal Freeze
 +
* September 1: liberty-3 -- align with string freeze, etc, open specs for M
  
TODO - what they all mean
+
* September 21st: Hard String Freeze, soon after that date expect to cut RC1 and open master for Mitaka
 +
* October 5th: cut a new tarball to include latest translations
 +
* October 12th: expect to bless most recent milestone as Liberty
  
TODO - exception process
 
  
== Special review days ==
+
OpenStack wide tracking of current progress:
 +
http://status.openstack.org/release/
  
* June 12: spec review day (to be confirmed)
+
Announcement of these dates on the mailing list: http://lists.openstack.org/pipermail/openstack-dev/2015-June/065819.html
* July 10: feature review bash day (to be confirmed)
 
* August 7: bug triage day (to be confirmed)
 
* September 11: bug review bash day (to be confirmed)
 
  
== How to get my feature merged? ==
+
=== Special review days ===
  
TODO
+
To make the above gates go smoother, we have some big review pushes:
 +
* June 12: spec review day
 +
** Focus on liberty specs not backlog specs: https://review.openstack.org/#/q/project:openstack/nova-specs+status:open+file:%255E.*liberty.*,n,z
 +
** https://review.openstack.org/#/q/project:openstack/nova-specs+status:open+file:%255E.*liberty.*,n,z
 +
* July 10: non-priority feature review bash day
 +
** Look at NeedCodeReview blueprints, and get more to complete: https://blueprints.launchpad.net/nova/liberty
 +
** Focus on the things considered ready to merge and non-priority here: https://etherpad.openstack.org/p/liberty-nova-priorities-tracking
 +
* August 5: bug triage day
 +
** Follow this process: https://wiki.openstack.org/wiki/BugTriage and https://wiki.openstack.org/wiki/Nova/BugTriage
 +
** Results: [[Nova/BugTriage#Liberty|Bug Triage Day - Liberty]]
 +
* August 12: bug review day
 +
** Try to get some bug fixes merged: http://status.openstack.org/reviews/
 +
* September 9th: release critical bug triage day
 +
** Look out for release blocking bugs, using: https://wiki.openstack.org/wiki/BugTriage
  
== Why bother? ==
 
  
We have agreed a list of priorities for the release here: http://specs.openstack.org/openstack/nova-specs/#priorities
+
All of these involve hanging out in #openstack-nova and working together to try and improve the statistics mentioned above.
  
Over previous release it became clear there are things we have to stop doing, to enable enough developer effort and review bandwidth to focus on priorities.
+
=== FAQs ===
  
If people are not working on priorities, its hoped they can either start helping some some of the priority efforts, or assist with bug fixing and bug triage.
+
For more details on process, please now see: [[Nova/Process]]

Latest revision as of 14:52, 19 October 2015

We are aligning with: Liberty_Release_Schedule But there are some extra deadlines around Priority features.

If you are new to Nova, please read this first: https://wiki.openstack.org/wiki/Nova/Mentoring


Dates overview

  • June 23-25: liberty-1 -- spec freeze for L, backlog stays open
  • July 16: non-priority feature proposal freeze
  • July 21-23: mid-cycle meetup
  • July 30: liberty-2 -- non-priority feature freeze
  • August 18: Feature Proposal Freeze
  • September 1: liberty-3 -- align with string freeze, etc, open specs for M
  • September 21st: Hard String Freeze, soon after that date expect to cut RC1 and open master for Mitaka
  • October 5th: cut a new tarball to include latest translations
  • October 12th: expect to bless most recent milestone as Liberty


OpenStack wide tracking of current progress: http://status.openstack.org/release/

Announcement of these dates on the mailing list: http://lists.openstack.org/pipermail/openstack-dev/2015-June/065819.html

Special review days

To make the above gates go smoother, we have some big review pushes:


All of these involve hanging out in #openstack-nova and working together to try and improve the statistics mentioned above.

FAQs

For more details on process, please now see: Nova/Process