Difference between revisions of "NeutronKiloProjectPlan"
(Created page with "This page tracks the Project Plan for Neutron during the Kilo release. === Dates === Given the focus on paying down technical debt, refactoring, spin outs and splits, we have...") |
|||
(One intermediate revision by the same user not shown) | |||
Line 1: | Line 1: | ||
This page tracks the Project Plan for Neutron during the Kilo release. | This page tracks the Project Plan for Neutron during the Kilo release. | ||
+ | |||
+ | We're following the broader project timelines here: | ||
+ | |||
+ | https://wiki.openstack.org/wiki/Kilo_Release_Schedule | ||
=== Dates === | === Dates === | ||
Given the focus on paying down technical debt, refactoring, spin outs and splits, we have aggressive SPD/SAD dates: | Given the focus on paying down technical debt, refactoring, spin outs and splits, we have aggressive SPD/SAD dates: | ||
− | * Spec Proposal Deadline: Monday | + | * Spec Proposal Deadline: Monday 12-8-2014 |
− | * Spec Approval Deadline: Monday | + | * Spec Approval Deadline: Monday 12-15-2014 |
Latest revision as of 16:59, 20 February 2015
This page tracks the Project Plan for Neutron during the Kilo release.
We're following the broader project timelines here:
https://wiki.openstack.org/wiki/Kilo_Release_Schedule
Dates
Given the focus on paying down technical debt, refactoring, spin outs and splits, we have aggressive SPD/SAD dates:
- Spec Proposal Deadline: Monday 12-8-2014
- Spec Approval Deadline: Monday 12-15-2014