Jump to: navigation, search

Mitaka Release Schedule

Revision as of 16:17, 25 September 2015 by Doug-hellmann (talk | contribs)
Week Development cycle milestones Other events
2015 October 19-23
26-30Mitaka Design Summit (Tokyo)
November 2-6
9-13
16-20
23-27
December 30-4mitaka-1 (Dec 1-3)
7-11
14-18
21-25
28-1
2016 January 4-8
11-15
16-22mitaka-2 (Jan 19-21)
25-29
February 1-5
8-12
15-19
22-26[FinalLibraryRelease]Final releases of all non-client libraries (Oslo and others)
March 29-4mitaka-3 (Mar 1-3) [FeatureFreeze] [Soft StringFreeze] [RequirementsFreeze] [FinalClientLibraryRelease]Final releases of client libraries with features from the cycle
7-11
14-18RC1 target week [Hard StringFreeze]N cycle PTLs self-nomination
21-25N cycle PTLs election
27-1Technical Committee member self-nomination
April 4-8Mitaka Release (Apr 7)Technical Committee member election
11-15
18-22
25-29N Design Summit (Austin)