Jump to: navigation, search

Difference between revisions of "Juno Release Schedule"

m
Line 18: Line 18:
 
''Important notes:''
 
''Important notes:''
 
* Swift does not publish intermediary milestones (juno-X). They may release extra versions.
 
* Swift does not publish intermediary milestones (juno-X). They may release extra versions.
* '''New features must land in master branch by September 2''', two days before juno-3 milestone delivery.
 
 
</td><td>
 
</td><td>
 
<table border="1" cellpadding="4" cellspacing="0">
 
<table border="1" cellpadding="4" cellspacing="0">

Revision as of 12:49, 22 May 2014

  • Status: Confirmed
  • PTLs for integrated projects:
    • Michael Still (Nova)
    • Mark Washenberger (Glance)
    • John Dickinson (Swift)
    • David Lyle (Horizon)
    • Dolph Mathews (Keystone)
    • Kyle Mestery (Neutron)
    • John Griffith (Cinder)
    • Eoghan Glynn (Ceilometer)
    • Zane Bitter (Heat)
    • Nikhil Manchanda (Trove)
    • Sergey Lukjanov (Sahara)
  • Release Manager: Thierry Carrez (ttx)


Important notes:

  • Swift does not publish intermediary milestones (juno-X). They may release extra versions.
Week (Thursday) Common Swift
2014 May 15Design Summit (Atlanta)
22
29
June 5
12juno-1
19
26
July 3
10
17
24juno-2
31
August 7
14
21FeatureProposalFreeze
28
September 4FeatureFreeze, StringFreeze
juno-3
11
18
25Release candidates
October 2
9
16Juno Release (2014.2.0)
23
30
November 6Design Summit (Paris)