- Status: Approved
- PTLs:
- Russell Bryant (Nova)
- Mark Washenberger (Glance)
- John Dickinson (Swift)
- Gabriel Hurley (Horizon)
- Dolph Mathews (Keystone)
- Mark McClain (Quantum)
- John Griffith (Cinder)
- Julien Danjou (Ceilometer)
- Steven Hardy (Heat)
- Mark McLoughlin (Oslo)
- Release Manager: Thierry Carrez (ttx)
New features must land in master branch by September 4, two days before havana-3 milestone delivery.
|
Week (Thursday) |
Common | Swift |
2013 |
April |
18th | Design Summit |
25th | | |
May |
2nd | | |
9th | | |
16th | | |
23rd | | |
30th | havana-1 | |
June |
6th | | |
13th | | |
20th | | |
27th | | |
July |
4th | | 1.9.0 (Jul 2) |
11th | | |
18th | havana-2 | |
25th | | |
August |
1st | | |
8th | | |
15th | | 1.9.1 (Aug 13) |
22nd | FeatureProposalFreeze: Nova & Cinder (Aug 21) Neutron & Heat (Aug 23) | |
29th | FeatureProposalFreeze: Keystone (Aug 28) | |
September |
5th | FeatureFreeze (Sep 4) StringFreeze (Sep 4) havana-3 (Sep 6) | |
12th | | |
19th | | |
26th | Release candidates |
October |
3rd |
10th |
17th | Havana Release (2013.2) |
24th | | |
31st | | |
November |
7th | Design Summit |
|