Grizzly Release schedule

  • Status: Approved
  • PTLs: Vish Ishaya (Nova), Brian Waldon (Glance), John Dickinson (Swift), Gabriel Hurley (Horizon), Joe Heck (Keystone), Dan Wendlandt (Quantum), John Griffith (Cinder), Mark McLoughlin (Oslo)
  • Release Manager: Thierry Carrez (ttx)

New features must land in master branch by February 19, two days before grizzly-3 milestone delivery.

Week (Thursday) Common
11>|2012 2>|October 18th
25th
5>|November 1st
8th
15th
22nd ¤ grizzly-1
29th
4>|December 6th
13th
20th
27th
16>|2013 5>|January 3rd
10th ¤ grizzly-2
17th
24th
31st
4>|February 7th
14th
21st FeatureFreeze (Feb 19)<
>StringFreeze (Feb 19)<
> ¤ grizzly-3
28th
4>|March 7th
14th 3>|Release Candidates
21th
28th
3>|April 4th
11th
18th