GrizzlyReleaseSchedule

Revision as of 10:07, 20 February 2013 by ThierryCarrez (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
  • Status: Approved
  • PTLs:
    • Vish Ishaya (Nova)
    • Brian Waldon (Glance)
    • John Dickinson (Swift)
    • Gabriel Hurley (Horizon)
    • Joe Heck (Keystone)
    • Dan Wendlandt (Quantum)
    • John Griffith (Cinder)
    • Mark McLoughlin (Oslo)
  • Release Manager: Thierry Carrez (ttx)


New features must land in master branch by February 19, two days before grizzly-3 milestone delivery.

Week (Thursday) CommonSwift
2012 October 18thDesign Summit
25th
November 1st
8th
15th1.7.5 (Nov 13)
22ndgrizzly-1
29th
December 6th
13th
20th
27th
2013 January 3rd
10thgrizzly-2
17th
24th1.7.6
31st
February 7th
14th
21stFeatureFreeze (Feb 20)
StringFreeze (Feb 20)
grizzly-3
28th
March 7th
14thRelease candidates
21st
28th
April 4thGrizzly Release (2013.1)
11th
18thDesign Summit