Jump to: navigation, search

Difference between revisions of "Cyborg/Victoria Release Schedule"

(Dates Overview)
Line 14: Line 14:
 
**[https://wiki.openstack.org/wiki/Nova/Victoria_Release_Schedule Nova Victoria Release Schedule]
 
**[https://wiki.openstack.org/wiki/Nova/Victoria_Release_Schedule Nova Victoria Release Schedule]
 
**[https://wiki.openstack.org/wiki/Network/Meetings#Announcements_.2F_Reminders Neutron Victoria Release Schedule]
 
**[https://wiki.openstack.org/wiki/Network/Meetings#Announcements_.2F_Reminders Neutron Victoria Release Schedule]
 +
 +
= Blueprints with milestone =
 +
According to the [https://etherpad.opendev.org/p/cyborg-victoria-goals approved goals in victoria] and each milestone dates above, developers can roughly track all the approved blueprints set with milestones in the following. But please be aware that this page is usually created at the beginning of a release cycle, and may not update-to-date with the development process. F or more update-to-date or specific information, please track the [https://storyboard.openstack.org/#!/board/216 Victoria Release Board ].
 +
  
 
= FAQs =
 
= FAQs =
  
 
Please see: [TODO(yumeng): add cyborg contributor doc link here Cyborg team process].
 
Please see: [TODO(yumeng): add cyborg contributor doc link here Cyborg team process].

Revision as of 09:21, 12 June 2020

Dates Overview

  • Cyborg roughly follows the general release schedule.
    • Jun 01 - June 05: Virtual PTG
    • Jun 15 - Jun 19: Victoria-1 milestone, ussuri legacy and doc,wiki freeze
    • Jul 27 - Jul 31: Victoria-2 milestone, cyborg spec freeze
    • Aug 31 - Sep 04: non-client library (Oslo etc) release freeze
    • Sep 07 - Sep 11: Victoria-3 milestone, Feature Freeze, final python-cyborgclient release, requirements freeze, Soft String Freeze
    • Sep 21 - Sep 25: RC1 and Hard StringFreeze
    • Oct 05 - Oct 09: Last release candidates
    • Oct 12 - Oct 16: Victoria release

Blueprints with milestone

According to the approved goals in victoria and each milestone dates above, developers can roughly track all the approved blueprints set with milestones in the following. But please be aware that this page is usually created at the beginning of a release cycle, and may not update-to-date with the development process. F or more update-to-date or specific information, please track the Victoria Release Board .


FAQs

Please see: [TODO(yumeng): add cyborg contributor doc link here Cyborg team process].