*Victoria milestone 1
 
*Victoria milestone 1
 
**Containerize Cyborg, remove OPAE dependency and sync with Kolla, Yumeng,https://storyboard.openstack.org/#!/story/2007810
 
**Containerize Cyborg, remove OPAE dependency and sync with Kolla, Yumeng,https://storyboard.openstack.org/#!/story/2007810
**Wiki page and doc update(Wiki - milestone1, CLI doc-milestone2, admin-milestone1 and contributor's guide-milestone2), Yumeng & Shogo https://storyboard.openstack.org/#!/story/2007809
+
**Wiki page and doc update(Wiki - milestone1, CLI doc-milestone2, admin-milestone2 and contributor's guide-milestone2), Yumeng & Shogo https://storyboard.openstack.org/#!/story/2007809
 
**Review and Merge Ussuri legacy: support python3 legacy, Brin's patch and https://storyboard.openstack.org/#!/story/2003219
 
**Review and Merge Ussuri legacy: support python3 legacy, Brin's patch and https://storyboard.openstack.org/#!/story/2003219
 
**Review and Merge other legacy related to infra(patch topics like: unittest.mock, drop_future_imports, drop_mock,reset_conf, tox etc.)
 
**Review and Merge other legacy related to infra(patch topics like: unittest.mock, drop_future_imports, drop_mock,reset_conf, tox etc.)

Revision as of 02:37, 18 June 2020

Dates Overview

  • Cyborg roughly follows the general release schedule.
    • Jun 01 - June 05: Virtual PTG
    • Jun 15 - Jun 19: Victoria-1 milestone, ussuri legacy and doc,wiki freeze
    • Jul 27 - Jul 31: Victoria-2 milestone, cyborg spec freeze
    • Aug 31 - Sep 04: non-client library (Oslo etc) release freeze
    • Sep 07 - Sep 11: Victoria-3 milestone, Feature Freeze, final python-cyborgclient release, requirements freeze, Soft String Freeze
    • Sep 21 - Sep 25: RC1 and Hard StringFreeze
    • Oct 05 - Oct 09: Last release candidates
    • Oct 12 - Oct 16: Victoria release

Blueprints with milestone

According to the approved goals in Victoria PTG and each milestone dates above, developers can roughly track all the approved blueprints set with milestones in the following. But please be aware that this page is usually created at the beginning of a release cycle, and may not update-to-date with the whole development process. For update-to-date and detailed blueprints and bug information, please track in the storyboard Cyborg Victoria Release Board. For development code, track in the Gerrit.

  • Nova-neutron-nova SmartNIC Integration
    • nova-spec,Xinran, milestone2, nova spec freeze(This may change according to nova and neutron suggestions)
    • features in nova and neutron, milestone3, feature freeze(This may change according to nova and neutron suggestions)