2016-05-20

Revision as of 01:22, 21 May 2016 by B3rnard0 (talk | contribs) (Forecast)

TL;DR

The number of Craton tasks completed this week1 (2016-05-16 to 2016-05-22) is 10 (an increase of 3 from the previous week). 4 tasks were added this week. The arrival rate is 1.22 tasks per day (an increase of 0.16 from last week); the throughput rate (completed tasks) is 0.83 tasks per day (an increase of 0.13 from last week). The cycle time (number of days to complete a task from when it was created to when it is development done) is 7.18 days (an decrease of 0.39 from the previous week).

1. Can potentially include obsoleted or non-impactful tasks.

Forecast

Based on our progress up to this point, a throughput rate of 0.83 tasks per day, and 16 remaining tasks, we are projecting a completion of on or about 2016-06-10. This forecast date will be revised based on increases or decreases to scope and changes to the throughput rate.

Monte Carlo Forecast

Summary statistics

Summary Statistics

Completed issues per week

Throughput Graph

Cumulative flow diagram (CFD)

Summary Statistics

Source Kanban board