BexarReleaseScheduleSpec

Revision as of 23:17, 9 November 2010 by ThierryCarrez (talk)

Summary

tbd

Release Note

tbd

Rationale

tbd

User stories

tbd

Assumptions

We want at least two more three-month cycles.

Design

Proposed Solution

This solution aims at releasing before Ubuntu FeatureFreeze (for Bexar) and at Ubuntu FinalFreeze (for C).

Pre-cycle Prep:

Oct 28 Nov 4

Cycle for Bexar:

Nov 18 Nov 25 Dec 2 Dec 9 Dec 16 Dec 23 Dec 30 Jan 6 Jan 13 Jan 20 Jan 27
BF FF GF
Development (9 weeks) QA

Cycle for C:

Feb 10 Feb 17 Feb 24 Mar 3 Mar 10 Mar 17 Mar 24 Mar 31 Apr 7
BF FF GF
Development (7 weeks) QA

This places the next design summit either the week of April 25 or the week of May 2nd.

Key

  • ODS: Openstack Design Summit, Tuesday to Friday.
  • BF: Branch merge proposal Freeze, Thursday. All branches should be proposed by BF.
  • FF: Feature Freeze, Thursday. All branches should be merged by FF.
  • GF: Gamma Freeze, Tuesday. Gamma release is used to test the release for critical issues.
  • RC: Release Candidate on Tuesday. Release on Thursday. Acts of god are required to change the RC.

Ubuntu dates

  • Feb 24: Natty Narwhal feature freeze
  • Apr 14: Natty Narwhal final freeze
  • Apr 28: Ubuntu 11.04 release
  • May 9: UDS-O (Budapest)

Implementation

tbd

Test/Demo Plan

n/a

Unresolved issues

tbd

BoF agenda and discussion

tbd