Latest revision as of 19:58, 26 June 2019
Dates Overview
Nova roughly follows the general release schedule.
- Apr 29-May 3: Open Infrastructure Summit and PTG
- Jun 6: t-1 milestone
- Jul 25: t-2 milestone, nova spec freeze
- Sep 5: non-client library (oslo, os-vif, etc) release freeze
- Sep 12: t-3 milestone, Feature Freeze, final python-novaclient release, requirements freeze, Soft String Freeze
- Sep 26: RC1 and Hard StringFreeze
- Oct 10: Last day for release candidates
- Oct 17: Train release
Special review days
- Apr 9: Pre-PTG spec review day 1
- Apr 16: Pre-PTG spec review day 2
- June 4: Spec review day
- July 2: Spec review day http://lists.openstack.org/pipermail/openstack-discuss/2019-June/007381.html
Virtual Sprint
- None scheduled
FAQs
Please see: Nova/Process and Nova/Mentoring