Difference between revisions of "BexarReleaseScheduleSpec"
Line 34: | Line 34: | ||
| Oct 28 | | Oct 28 | ||
| Nov 4 | | Nov 4 | ||
+ | | Nov 11 | ||
|- | |- | ||
| | | | ||
| | | | ||
+ | | ODS | ||
|- | |- | ||
|} | |} | ||
Line 42: | Line 44: | ||
Cycle for Bexar: | Cycle for Bexar: | ||
{| border="1" cellpadding="2" cellspacing="0" | {| border="1" cellpadding="2" cellspacing="0" | ||
− | |||
| Nov 25 | | Nov 25 | ||
| Dec 2 | | Dec 2 | ||
Line 54: | Line 55: | ||
| Jan 27 | | Jan 27 | ||
|- | |- | ||
− | |||
| | | | ||
| | | | ||
Line 66: | Line 66: | ||
| GF | | GF | ||
|- | |- | ||
− | |colspan=" | + | |colspan="8" | Development (8 weeks) |
|colspan="2" | QA | |colspan="2" | QA | ||
|} | |} | ||
Line 101: | Line 101: | ||
* ODS: Openstack Design Summit, Tuesday to Friday. | * ODS: Openstack Design Summit, Tuesday to Friday. | ||
+ | * SD: Bexar specs submission deadline (Thursday) | ||
* BF: Branch merge proposal Freeze, Thursday. All branches should be proposed by BF. | * BF: Branch merge proposal Freeze, Thursday. All branches should be proposed by BF. | ||
* FF: Feature Freeze, Thursday. All branches should be merged by FF. | * FF: Feature Freeze, Thursday. All branches should be merged by FF. |
Revision as of 20:05, 10 November 2010
- Launchpad Entry: bexar-release-schedule
- Created: 2011-11-03
- Contributors: ThierryCarrez
Summary
tbd
Release Note
tbd
Rationale
tbd
User stories
tbd
Assumptions
We want at least two more three-month cycles.
Design
Proposed Solution
This solution aims at releasing before Ubuntu FeatureFreeze (for Bexar) and at Ubuntu FinalFreeze (for C).
Pre-cycle Prep:
Oct 28 | Nov 4 | Nov 11 |
ODS |
Cycle for Bexar:
Nov 25 | Dec 2 | Dec 9 | Dec 16 | Dec 23 | Dec 30 | Jan 6 | Jan 13 | Jan 20 | Jan 27 |
BF | FF | GF | |||||||
Development (8 weeks) | QA |
Cycle for C:
Feb 10 | Feb 17 | Feb 24 | Mar 3 | Mar 10 | Mar 17 | Mar 24 | Mar 31 | Apr 7 |
BF | FF | GF | ||||||
Development (7 weeks) | QA |
This places the next design summit either the week of April 25 or the week of May 2nd.
Key
- ODS: Openstack Design Summit, Tuesday to Friday.
- SD: Bexar specs submission deadline (Thursday)
- BF: Branch merge proposal Freeze, Thursday. All branches should be proposed by BF.
- FF: Feature Freeze, Thursday. All branches should be merged by FF.
- GF: Gamma Freeze, Tuesday. Gamma release is used to test the release for critical issues.
- RC: Release Candidate on Tuesday. Release on Thursday. Acts of god are required to change the RC.
Ubuntu dates
- Feb 24: Natty Narwhal feature freeze
- Apr 14: Natty Narwhal final freeze
- Apr 28: Ubuntu 11.04 release
- May 9: UDS-O (Budapest)
Implementation
tbd
Test/Demo Plan
n/a
Unresolved issues
tbd
BoF agenda and discussion
tbd