Nova/Ocata Release Schedule
Dates Overview
Nova roughly follows the general release schedule.
- Oct 25-28: Design summit in Barcelona
- Nov 17: o-1 milestone, spec approval freeze
- Dec 15: o-2 milestone
- Jan 11: Ocata blueprint review sprint: https://etherpad.openstack.org/p/nova-ocata-feature-freeze
- Jan 19: final non-client library release (oslo)
- Jan 26: o-3 milestone, final python-novaclient release, FeatureFreeze, Soft StringFreeze
- Feb 2: RC1 and Hard StringFreeze
- Feb 23: Ocata release
Special review days
- Monday November 14th: Spec review sprint: http://lists.openstack.org/pipermail/openstack-dev/2016-November/107152.html
Virtual Sprint
- TBD
FAQs
Please see: Nova/Process and Nova/Mentoring