- Status: Confirmed
- Integrated programs PTLs:
- Russell Bryant (Nova)
- Mark Washenberger (Glance)
- John Dickinson (Swift)
- David Lyle (Horizon)
- Dolph Mathews (Keystone)
- Mark McClain (Neutron)
- John Griffith (Cinder)
- Julien Danjou (Ceilometer)
- Steve Baker (Heat)
- Michael Basnight (Trove)
- Release Manager: Thierry Carrez (ttx)
Important notes:
- Swift does not publish intermediary milestones (icehouse-X). They may release extra versions.
- New features must land in master branch by March 4, two days before icehouse-3 milestone delivery.
|
Week (Thursday) |
Common |
Swift |
2013 |
November |
7th | Design Summit |
14th | | |
21st | | |
28th | | |
December |
5th | icehouse-1 | |
12th | | 1.11.0 (Dec 12) |
19th | | |
26th | (End-of-year holidays) |
2014 |
January |
2nd |
9th | | |
16th | | |
23th | icehouse-2 | 1.12.0 (Jan 28) |
30th | | |
February |
6th | | |
13th | | |
20th | FeatureProposalFreeze (Feb 18) | |
27nd | | |
March |
6th | FeatureFreeze, StringFreeze (Mar 4) icehouse-3 (Mar 6) | 1.13.0 (Mar 3) |
13th | | |
20th | | |
27th | Release candidates |
April |
3rd |
10th |
17th | Icehouse Release (2014.1.0) |
24th | | |
May |
1st | Recommended "Off" week |
8th | | |
15th | Design Summit |
|